M4 solar farm the size of 120 football pitches to be built

3
Skip to next photo
1/1
Show caption
1/1
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.
Close Icon

Find, save and share Public Notices that affect you in the area.

Search the Public Notice Portal What is the Public Notice Portal?

What is the Public Notice Portal?

The Public Notice Portal carries statutory public notices published in local newspapers and is the fastest and most effective way of finding out what is happening in YOUR neighbourhood.

Search the Public Notice Portal

A huge solar energy scheme capable of generating enough electricity to power thousands of homes has been given the green light on farmland near the M4 - despite concerns over its impact on the countryside.

Wiltshire Council has granted planning permission for the Flaxlands Solar Farm at Flaxlands Farm, between Royal Wootton Bassett and Hook.

The development will include a 49.9-megawatt solar farm spread across around 87 hectares of land, alongside a large battery energy storage system, electrical infrastructure and new habitat creation areas.

The scheme will occupy land either side of Flaxlands Lane and is expected to operate for up to 40 years before being removed and the site restored to agriculture.

Planning officers concluded that the project's contribution to renewable energy generation, energy security and carbon reduction outweighed concerns about its visual impact and the temporary loss of farmland.

In their report, officers described the development as making a "significant contribution" towards net-zero targets and said national planning policy requires substantial weight to be given to renewable energy schemes.


For the latest public notices and planning applications in your area, visit www.publicnoticeportal.uk


The council acknowledged that the project would bring "industrialising change" to a largely rural landscape.

Extensive rows of solar panels, fencing, substations, battery storage units and a 15-metre communications tower will alter views across the area, particularly for walkers using public rights of way and residents living closest to the site.

Landscape officers said the development would cause "moderate localised landscape harm" and change the character of the countryside around Flaxlands Lane. However, they concluded that woodland planting, habitat creation and screening measures could reduce, though not eliminate, the impact.

The proposal proved divisive during consultation.

Twenty-nine objections were lodged, with residents raising concerns about the loss of agricultural land, construction traffic on narrow rural lanes, fire risks linked to battery storage, impacts on wildlife and what some described as the creeping industrialisation of north Wiltshire's countryside.

Lydiard Tregoze Parish Council also objected, citing concerns over heavy construction traffic passing through Hook and questioning the use of productive farmland for energy generation.

But the scheme also attracted 25 letters of support. Backers argued that large-scale renewable energy projects are essential to tackle climate change, improve energy security and reduce reliance on fossil fuels. Supporters also pointed to biodiversity gains and opportunities for grazing sheep around the solar arrays.

Environmental concerns prompted significant changes to the layout before approval was granted. Natural England originally objected because parts of the proposal would have affected the Flaxlands Manor County Wildlife Site. Revised plans removed solar panels from the protected grassland area and introduced additional ecological buffers.

The final scheme includes habitat management measures, protection for ancient woodland, mitigation for bats, skylarks, great crested newts and water voles, and long-term biodiversity improvements expected to last at least 30 years.

A battery energy storage facility capable of storing up to 49.9MW of electricity will form part of the project. Developers submitted a fire safety strategy and committed to installing monitoring, suppression and containment systems. Dorset and Wiltshire Fire and Rescue Service raised no objection subject to safeguards being put in place.

Construction traffic remains one of the most contentious issues. More than 1,000 vehicle movements are expected during the six-month build period, with temporary passing places required on Flaxlands Lane. Wiltshire Council's highways team accepted the impact could be managed through strict traffic controls and planning conditions.

The site is predominantly Grade 3b agricultural land, although around 10.4 hectares is classified as Grade 3a "best and most versatile" farmland. Officers accepted that some productive land would be taken out of food production but said the loss would be temporary and that sheep grazing could continue beneath the panels.

In the final planning balance, Wiltshire Council concluded that the renewable energy benefits, biodiversity improvements and contribution to energy security outweighed the landscape harm and agricultural land impacts.

The solar farm must be decommissioned after its operational life ends, with the land restored to its previous agricultural use.